New Homes in Hanley Swan

DJD Architects worked originally for the landowner to, initially secure allocation of the site in the Local Plan and then secure outline planning approval.  

Working for Signature New Homes, who purchased the site, we developed detailed proposals for 16 no. new homes, with a mix of open market, shared ownership and affordable rent tenures.  Reserved Matters approval was secured in November 2019.

The design extends out the existing shared surface, maintaining the views through the site to the Malvern Hills.  Working with BEA Landscape Architects and Bannersgate engineers the proposals have been developed so that the built form, soft landscaping and engineering, including SUDS support are in harmony.

DJD Architects were retained by J Harper and Sons (Leominster) Ltd who won the design and build contract for construction of the properties.  Work started on site in spring / summer 2020, handing over in spring 2021. 

Photographs by Signature New Homes